BIZ SPONZORS
popular biz reading
Marketing Mix: Promotion
Employee Turnover
Marketing Mix: Price
Planning and Organizing
Maslow's Hierarchy of Needs
Key Performance Indicators
Sustainable Competitive Advantage
Ishikawa Fishbone Diagram
Price Determination
Supply Chain Concept
Employee Induction
3 Basic Finance Statements
Sales Forecast Accuracy
FMCG Sales Boosting
OTIF - On Time In Full
Merchandising at the Point of Sales
Promotion Mix: Advertising
Employee Motivation
Porter's 5 Forces
CHECK ON BIZ DEVELOPMENT
biz sponsors
BrainCast Relaxation
Advertise on Biz Development
My BrainCast
Energy Booster
Twitter
biz archive
2012
2011
2010
2009
2008
2007

My Introspective

by Laurus Nobilis
My BrainCast

Performance Management

PROJECT MANAGEMENT
Resources and Budget Planning (E)

 

Project Management

 

 

What is the project? How to select and justify the project? How to plan and execute the project?

 

Posted: Sep 2010


 

Project Resource Planning

Resources planning is a detailed planning of required materials, equipment, services … There are three different types of resource requirements planning used for developing a project schedule. Those three types are unlimited resource scheduling, time-limited resource scheduling, and resource-limited resource scheduling.

  • Unlimited resource scheduling. 
    Unlimited resource scheduling assumes that resources are available whenever and wherever the resource they are needed. Unlimited resource scheduling gives the project its earliest completion date and is the most optimistic.
     

  • Time-limited resource scheduling.
    In time-limited resource scheduling, resources that are available are identified as they are, while the time is limited. If the available resources need to finish the task on time, they need to work overtime, if the task deployment is behind schedule.
     

  • Resource-limited resource scheduling
    In resource-limited resource scheduling, the resources may be limited, so the project extra time could be needed, since employment of additional resources is not possible.

 
The Budget Planning

Once the resources are identified and the project’s timeline is defined, it is time to assign costs and resources to each of the tasks. Two types of budgets can be developed for the same project. The first is a preliminary cost estimate. The second type of budget is a final cost estimate.

 

Preliminary cost estimate

Project Management is a management method that is used to plan, organize and control project activities. The project is initiated by executive committee that will initiate project work.The basic concept of Project Management is the delegation of general management authority to the Project Leader.



This type of budget is typically done when there is little time available to provide a more complete picture of budget requirement. The purpose of preliminary cost estimate is roughly estimation of project financial feasibility.

Final cost estimate

This type of budget is very detailed, and is typically used to support project planning and implementation. The project’s actual costs should be typically between 5 and 10 percent of variation from budget.

Both type of budget is used, both have key components:

  • Labor

  • Materials 

  • Machines  

  • Supplier or consultant costs 

Another aspect of planning is the contingency planning. These are unexpected events that can happen during a project. An example is a machine breakage, delayed delivery of specific material. All these are considered project risks that may need to be allowed for.


Continue on Project Management:
 
1. Project Management Overview 
2. 9 Areas of Project Management 
3. Project Lifecycle – 5 Stages of Project  
4. How to Determinine a Value of the Project? 
    4.1. Simple Payback 
    4.2. Average Return on Investment (ROI) 
    4.3. Net Present Value (NPV) 
    4.4. Internal Rate of Return (IRR) 
    4.5. Cost/benefit analysis 
    4.6. Time value of money 
    4.7. Present value of future payments 
    4.8. Justification of Addopted project 
5. Project Planning – Project Charte
6. Work Cascading Structure (WBS) 
7. Project Scheduling ( Arrow-on-Arrow and Gantt Chart ) 
8. Project Scheduling  ( CPM and PERT ) 
9. The Responisbility Matrix 
10. Resources and Budget Planning 
11. Clasification of Projects

 

 

My BrainCast Self Improvement
blog comments powered by Disqus
 
     
My BrainCast My BrainCast energy Booster My Braincast Deep Sleep
My BrainCast Mandala Meditation My BrainCast Relaxation
my-braincast